Quick answer
Define which weekdays are working days, count eligible dates in the range, and skip any holiday dates from the calendar you are using.

Step by step
- Decide whether the start and end dates count. The example includes both endpoints if they are working days.
- Mark weekends under the schedule you use. For a Monday–Friday schedule, a complete seven-day block contributes five weekdays.
- Remove holidays only if they occur on counted workdays. In Google Sheets use
=NETWORKDAYS(A2,B2,E2:E10)for a Saturday–Sunday weekend, with holiday dates in column E.
Worked examples
Monday through Friday
Nov 9–13, 2026 includes five weekdays on a Monday–Friday schedule. If Wednesday Nov 11 is on your holiday list, the count is four.
A weekend holiday
Extending the range through Sunday Nov 15 still gives four workdays. Listing Saturday Nov 14 as a holiday does not reduce the count again.
What to check
The Days Between Dates calculator shows all calendar days. Use a holiday list and a workweek definition when the task calls for business days.